West Salisbury Street (U.S. 74) closes at the Lees Cut bridge in Wrightsville Beach from 5 a.m. Monday, Nov. 30. NCDOT expects the new bridge by summer 2027.
West Salisbury Street, one of the two roads onto Wrightsville Beach, closes at 5 a.m. Monday at the Lees Cut bridge. It is not expected to reopen until summer 2027.
Wrightsville Beach is about eight miles east of downtown Wilmington. The N.C. Department of Transportation’s contractor, Balfour Beatty, plans to fully close the road, which is U.S. 74, from Pelican Drive to Lookout Harbor Way. That is according to an NCDOT news release.
Crews will demolish the old bridge over Lees Cut and build a new one. NCDOT said no cars and no pedestrians will be allowed in the work zone.
What it means for you
- From Monday, Nov. 30: you cannot drive, walk or bike across the Lees Cut bridge on West Salisbury Street.
- Other way on: Causeway Drive (U.S. 76) is the other road onto the island. NCDOT’s release names no signed detour.
- How long: NCDOT expects the new bridge to be finished by summer 2027. The state’s DriveNC traffic map lists the closure through May 1, 2027.
- The start date can still move. NCDOT said it depends on finishing the utility relocation now underway.
- Alerts: NCDOT sends closure notices by text or email. Sign up on its Wrightsville Beach bridge traffic alerts page.
What the new bridge will have
NCDOT’s release lists:
- two 12-foot travel lanes, one each way
- two 6-foot bike lanes
- a 12-foot multi-use path on the south side
The first of three bridges
The Lees Cut bridge is Phase 1 of a larger job. NCDOT is replacing three bridges onto Wrightsville Beach, according to its project page:
- the West Salisbury Street (U.S. 74) bridge over Lees Cut
- the longer West Salisbury Street bridge over Banks Channel, which crews move to next
- the Causeway Drive (U.S. 76) bridge over Banks Channel
NCDOT says all three are safe but near the end of their life. It estimates the whole project at $105 million. That breaks down as $70.8 million for construction, $32.2 million for property and $2 million for utilities.
NCDOT awarded the Phase 1 contract to Balfour Beatty for $8.67 million, according to an Oct. 1 NCDOT release. The department said the contracting method it is using could finish the project up to two years sooner than the traditional route.
Have your say